This morning the concrete floor of the NE elevation is being poured, ready for the terrace outside the cafe.
Inside the central hoardings the steel work for the lift will be installed. We will be making some changes to the Library layout as we prepare for new hoardings out to the East Wing, so a further update can be found here later in the week. The Level 2 display shelves will be affected and parts of NZC and Law.